FirstEnergy reserves turbines for 1.2 GW data‑center project and seeks 3 GW more in West Virginia

FirstEnergy’s two utilities have set aside combined‑cycle turbines for a 1.2‑gigawatt data‑center power project in West Virginia and have opened a solicitation for an additional three gigawatts, expanding its data‑center pipeline for Q3.

FirstEnergy’s two utilities in West Virginia have earmarked combined‑cycle turbines to supply a 1.2‑gigawatt power project that will serve data‑center customers, company officials said.

The utilities also released a solicitation seeking contracts for an extra three gigawatts of capacity, further extending FirstEnergy’s data‑center pipeline for the third quarter.

Sources1

Reporting and evidence linked in this story.

  1. Utility DiveFirstEnergy data center pipeline increases to 26 GW in Q3
Claim connections1

FirstEnergy utilities reserved combined-cycle turbines for a 1.2 GW data center‑focused project in West Virginia and issued a solicitation for an additional 3 GW, company officials said.