# US Power Grid Stalls as Single Mill Produces Crucial Transformer Steel

The US power grid faces a critical supply chain bottleneck for large power transformers, with demand tripling since 2019 and delivery times exceeding three years due to a shortage of grain\-oriented electrical steel manufactured by just one domestic mill\.

Canonical URL: https://allnews.crickdevs.com/article/us-power-grid-stalls-as-single-mill-produces-crucial-transformer-steel-55b8a3e0

Publisher: AllNews

Author: AllNews Editorial

Category: Energy

Published: 2026-11-05T17:14:12.676Z

Updated: 2026-11-05T17:14:12.676Z

Energy infrastructure projects ranging from renewable expansions to data centers are facing delays due to a shortage of large power transformers, equipment that has maintained a largely unchanged design since the late 19th century\. These massive structures, which can weigh as much as 400 tons, are currently aging beyond their intended lifespans across the US and globally, creating an urgent need for replacements that the current supply chain cannot meet\.

Demand for generator step\-up transformers nearly tripled between 2019 and 2025, while orders for distribution transformers more than doubled, driving costs up by approximately 80%\. The primary hurdle is not the transformer assembly itself, but the provision of grain\-oriented electrical steel, a specialized material with precisely aligned magnetic crystals required to minimize energy loss\. Currently, only one mill in the United States possesses the technology to produce this essential component, creating a concentrated point of failure for the energy sector\.

Because these transformers are custom\-engineered rather than mass\-produced, utilities and power producers are facing lead times of more than three years for new equipment orders\. These delays directly impact the ability to connect new power sources, such as solar farms or gas plants, to the transmission grid, regardless of the energy source\. The bottleneck in steel production effectively holds back the physical infrastructure required to expand electrical capacity and maintain grid reliability for future energy demands\.

## Summary

- Demand for generator step\-up transformers nearly tripled between 2019 and 2025, while distribution transformer orders more than doubled, driving costs up by approximately 80%\.

- Large power transformers face delivery delays exceeding three years because they are custom\-engineered and rely on grain\-oriented electrical steel, which only one domestic mill can produce\.

## Revision note

Initial brief generated from a single permitted source dated November 4, 2026\.

## Image

[File photo: US Digital Economy Power Grid Costs Spark Senate Debate](<https://media.allnews.crickdevs.com/approved/05182059-fe01-415a-854c-801375f345eb-95862842-13c5-4cf2-b6be-439005562113.webp>)

 · en\.cryptonomist\.ch / License metadata unavailable

[Image source and licence](<https://en.cryptonomist.ch/2026/10/14/us-digital-economy-power-grid/>)

## Sources

- [America’s grid upgrade hinges on a 400\-ton machine designed in the 1800s — and just one U\.S\. mill makes the special steel inside it](<https://fortune.com/2026/11/04/power-transformer-shortage-grid-400-ton-electrical-steel-one-us-mill/>) — Fortune

## Claim connections

- Demand for generator step\-up transformers nearly tripled between 2019 and 2025, and orders for transformers that lower voltage for local distribution more than doubled, with costs increasing by 80%\. (confirmed)
  - [Source](<https://fortune.com/2026/11/04/power-transformer-shortage-grid-400-ton-electrical-steel-one-us-mill/>)

- Only one steel mill in the US currently has the technology to produce grain\-oriented electrical steel, which is a key ingredient in large power transformers\. (confirmed)
  - [Source](<https://fortune.com/2026/11/04/power-transformer-shortage-grid-400-ton-electrical-steel-one-us-mill/>)